Installation Process

Modular Mast - Stages of modular mast (WP3, WP4 and WP5) installation

Modular masts are ideally installed by two teams working sequentially.

Stages 1-2 Team 1

1

Install steel lower mast section and secure to foundation.

2

Install steel upper core mast and secure to lower mast.

Stages 3-4 Team 2

3

Slide further sleeve modules over upper core and lower into position.

4

Install steel lower mast section and secure to foundation.

Stages 5-7 Team 2

5

Stack required number of sleeves, making electrical connections progressively.

6

Secure mast cap and lamp arm to top of core mast. Attach lamphead and connect power cables.

7

Boot up and verify control unit and batteries.

Lightweight Mast - Stages of the lightweight masts (WP1L and WP2L) installation

Lightweight Masts are designed for low cost logistics and a simple installation process.

Masts are shipped on modular pallets in standard end-loading containers. Once on site the masts can be erected by two persons without the use of cranes or access platforms.

1

The masts can be offloaded from a truck by hand and carried to site by two people. The base plate is connected to the foundation.

2

A removable hinged coupling enables the mast to be connected to the base plate and the mast is then simply raised to its vertical position.